The Chesterton Utility has finalized the issuance of the first batch of
sewer revenue bonds--which could total up to $5.1 million--and now it’s time
for staff to hit the drawing boards.
Town Attorney Chuck Lukmann told the Utility Service Board at its meeting
Monday night that the projects to be funded with the bonds should be
designed and the specs put out for bid as soon as possible.
Included in the first wave of projects will be the long-discussed,
long-postponed Downtown sanitary sewer separation and replacement, estimated
to cost $672,000, the single most expensive item on the Utility’s to-do
list. Town Engineer Mark O’Dell said that this project is currently slated
for next April
Other projects or purchases to be funded by the bonds: the repair of the
Morningside subdivision sewer supports and bridge and the re-lining of that
sewer under the railroad right-of-way; the purchase and installation of new
blowers at the wastewater treatment plant to reduce energy use; and the
purchase and installation of variable frequency drivers for the influent
pumps at the plant.
The first batch of bonds were sold in sub-batches at interest rates of 4.25
percent, 4.35 percent, and 4.5 percent, significantly less than the maximum
rate of 7.5 percent authorized by the issuing ordinance approved by the Town
Council in June. The bonds will be repaid with revenues from customers’
sanitary sewer rate payments.
In December 2008 the Town Council increased that rate by 14 percent,
effective Jan. 1, 2009, on the split recommendation of the Service Board,
which requested a single-phase hike in order to put the Utility in the
position to issue bonds. Members John Schnadenberg and Jim Raffin preferred
to see a two-phase hike, with a 7-percent increase this year and another
7-percent increase in 2010.
That hike raised the average residential customer’s bimonthly sanitary sewer
bill from $66 to $77.25.
Currently around $3,080,000 remains outstanding on a sewer revenue bond
issued in 2001 for the purpose of financing the expansion of the wastewater
treatment plant.
Projects in the
Works
In other business, O’Dell told the Service Board that the upgrade of the
Dickinson Road lift station--whose entire cost is being borne by the Lake
Erie Land Company--is well under way, with the boring under Ind. 49 now
completed. Today the contractor, Woodruff & Sons of Michigan City, was
scheduled to begin the installation of an additional force main beneath the
eastbound lane of East Porter Ave. from Ind. 49 to South Calumet Road.
The Dickinson Road lift station pumps virtually all wastewater generated
east of Ind. 49 on its way to the treatment plant, first west via the East
Porter Ave. force main and then north via the huge Eighth Street gravity
main.
In conjunction with that project, members voted 4-0 to authorize O’Dell to
prepare a scope of project for the replacement of that ductile iron force
main between South Calumet Road and Fifth Street. Schnadenberg was not in
attendance. Last summer it was discovered that the force main serving the
Dickinson Road lift station between South Calumet and Eighth Street had
prematurely corroded and the piece of main between Fifth Street and Eighth
Street was accordingly replaced with PVC. The rest of the main, though it
has been temporarily bypassed, is still in the ground and needs likewise to
be replaced with PVC.
Meanwhile, O’Dell said, consultant SEH Inc. continues to work with the U.S.
Army Corps of Engineers on the design of a re-line of the 19-inch gravity
main beneath West Porter Ave. U.S. Rep. Pete Visclosky, D-1st, has secured
an earmark of $300,000 for that project, which the Utility will match with
$100,000 of its own. On top of that, the Utility is paying SEH up to $54,600
to shepherd the project through the federal bureaucracy. The re-line should
be done in October.
From Septic to
Sanitary
Members voted 4-0 to authorize Lukmann to draft a tie-in agreement with the
homeowner at the southwest corner of 100E and 1100N, after it was discovered
that his septic tank encroaches by four feet into the right-of-way purchased
from the homeowner as part of the South Calumet District project.
The homeowner has been extremely cooperative throughout the process, Lukmann
noted, and would have been happy to tie in to the sanitary sewer system had
he known at the time that his septic tank was in the purchased right-of-way.
DLZ Flow
Monitoring
Members also voted 4-0 to authorize a payment of $10,000 to long-term
control plan consultant DLZ, which is conducting flow-monitoring under an
order by the Indiana Department of Environmental Management as part of the
Utility’s development of a long-term control plan to reduce the number of
combined sewer overflows caused by rain events.
The flow monitoring, O’Dell reminded the Service Board, is an open-ended
commitment. “IDEM says we have to do this monitoring while Porter is doing
its own monitoring,” he said.
July in Review
In July Chesterton used 54.32 percent of its 3,752,000 gallon per day (gpd)
allotment at the wastewater treatment plant; Porter, 50.83 percent of its
767,000 gpd allotment; the Indian Boundary Conservancy District, 58.25
percent of its 81,000 gpd allotment; and the plant as a whole, 53.50 percent
of its capacity.
There were no bypasses in July, with rain totaling 2.9 inches.
In July the Utility ran a surplus of $177,340 and in the year-to-date is
running a deficit of $50,909.
Welcoming the
Super
The Service Board spent a few moments at the end of the meeting welcoming
newly hired Superintendent James Chris Shank on his first day on the job.
“It’s good to have you here,” Member Andy Michel said. “I hope you feel the
same way. You’re stepping into a lot but you’ll be getting a lot of help.”
Member Scot McCord urged Shank to feel free to call on the Service Board at
any time. “I think we made a pretty good choice,” he said.
With the $5.1-million bond issue in mind, President Larry Brandt wished
Shank good luck. “You’re going to need some,” he said. “But you’ve got a
good team to work with.”
Shank is a Class III certified operator with eight years of experience in
charge of the Whiteland wastewater treatment plant in Johnson County, Ind.