The Indiana Department of Transportation (INDOT) has announced that a route
transfer agreement has been signed with the City of East Chicago to
relinquish sections of Riley Road and Dickey Road to INDOT.
Effective October 1, this agreement will INDOT to reroute Ind. 912 (Cline
Ave.) as part of the Cline Ave. traffic solution plan.
In mid-April, INDOT announced a multi-project traffic solution designed to
address the displaced traffic due to the closure of the Cline Ave. bridge.
One key element in the design solution is transferring sections of Riley and
Dickey roads in the City of East Chicago. This transfer will enable INDOT to
construct a new ramp from Cline Ave. to Dickey Road as well as to undertake
additional improvements along these roads.
“Thanks to the hard work of INDOT staff and Mayor Pabey of East Chicago and
his staff, we are transferring Riley and Dickey roads to INDOT, which allows
us to move forward with our Cline Ave. traffic solution,” INDOT Chief of
Staff Bob Zier said. “Since we announced the bridge would not reopen to
traffic, our team of staff and consultant engineers has been working
diligently with the local communities conducting numerous meetings and
discussions to understand the traffic needs of the businesses and residents
to determine the most appropriate solution. The signing of the route
transfer agreement is a culmination of the positive partnerships formed over
the past few months.”
Riley Road from the Cline Ave. interchange to the Dickey Road intersection
will be transferred to INDOT as well as Dickey Road from the Riley Road
intersection to just northwest of Michigan Avenue, including the draw bridge
on Dickey Road.
The transfer total is 1.39 centerline miles.
Design plans for the new ramp from Cline Ave. to Dickey Road will move
forward in addition to the rehabilitation of two of the Riley to Cline Ave.
ramps that will remobilize traffic west of the bridge. The lift bridge on
Dickey Road will also be upgraded to an automated lift bridge to function
similar to that of the U.S. 12/20/Ind. 152 (Indianapolis Boulevard) lift
bridge. Today the Dickey Road bridge is raised and lowered manually.
The Riley Road ramp improvement project was awarded last week to Walsh
Construction for $2.2 million. The project will reconstruct the Riley Road
ramp to Cline Ave. to allow Riley Road traffic to access westbound Cline
Ave. The traffic patterns that establish once the ramp opens this fall will
help determine if and when the ramp will accommodate eastbound traffic.
The first project as part of the Cline Ave. traffic solution is already
under construction: re-surfacing the Michigan Ave. ramp to Cline Ave. in
East Chicago near ArcelorMittal Steel. This project will mill the concrete
surface of the ramp and replace it with asphalt. A temporary ramp from
Michigan Ave. to Cline Ave. just north of the existing ramp will be
constructed as part of the project. Once the temporary ramp is built,
traffic will use the newly constructed ramp whiles crews resurface the
existing ramp.
Initial work on the Michigan ramp is already underway with no current road
restrictions. During the week of July 26 crews will begin milling the
existing pavement and resurface the roadway. Work will take place during the
evening and overnight hours from 6:30 p.m. and 5:30 a.m. to lessen the
impact on traffic, especially during shift changes. One direction of traffic
will be guided through the area during those hours.
The Cline Ave. bridge was originally constructed and opened to traffic in
1983. In 1999, INDOT began noticing structural deficiencies that required
closer monitoring with increased inspections and programming a bridge
rehabilitation project. In 2006, INDOT hired a consultant to conduct
detailed inspections every six months. In November 2009, INDOT began a
temporary closure of the bridge to all traffic while a more detailed review
was conducted to determine the overall safety of the bridge. On December 28,
INDOT announced that Cline Ave. between Michigan and Calumet would not
reopen to traffic due to the diminished state of the structural integrity of
the bridge.
INDOT will continue to work with the City of East Chicago and other
community partners, including the Regional Development Authority and area
casinos, to help enhance the overall mobility and safety of the interchanges
on Cline Ave. at Jeorse Park and the Indiana Toll Road. Designs for both
interchange improvements are still conceptual, although INDOT is committed
to working with these community partners to determine the appropriate
traffic and capacity needs, identifying funding sources, and incorporating
design elements in the spirit of cooperation.