SUNSET HILL FARMS
COUNTY PARK – EDUCATION CENTER RFP
REQUEST FOR
PROPOSALS (RFP)
The Porter County
Parks and Recreation Department (hereinafter, the Department) is soliciting
proposals from contractors (hereinafter, the Contractor) to construct a
Barn-Style Education Center in Sunset Hill Farm County Park. The Department
will select a firm to provide construction services for completion of the
project based on the following Request for Proposal (RFP).
Anticipated
construction & design components include:
Use of
traditional post and beam framing
Management of
state and county permitting and approval process
Grading and
earthwork
Cost estimate for
operating budget
Cost estimate and
schedule of needed capital items by date
Recommended
priorities and phasing of improvements
Known issues and
potential components to be addressed in the project are:
Drainage and
storm water management
Desire to
incorporate LEED criteria wherever possible to mitigate environmental and
natural resource impact
Associated
signage, including way finding, identification and traffic control
Review of designs
for lighting, site furnishings and other such elements
Location, and
design of centralized concessions, restrooms, water fountains, shelters and
other comfort and safety facilities
Utilities
assessment including underground sewer and water connections
Potential for
naturalizing water conveyances including use of ponds
The building will
be developed in response to input from the Department, and will include
Department program staff, natural resources managers and maintenance staff.
In addition, the plan will reflect public input as endorsed by the
Department and major stakeholders.
Project Process
The project will
be completed, generally, as follows:
1. Meet with the
Department, architect and other stakeholders to review current construction
drawings, existing information and coordinate tasks between Department and
Contractor.
2. Conduct site
and facility analyses as necessary.
3. Public park
Board meetings in cooperation with the Department.
4. Produce
updated construction documents based on site and facility conditions,
program plan, project parameters, fundraising progress and guidance provided
by the Department, stakeholders and funding requirements.
5. Execution of
design and construction plans.
Resources that
will be made available to the Contractor:
1. Topographic
survey of immediate area
2. Meeting
minutes and notes as appropriate to this project
The Contractor
shall:
1. Prepare all
necessary design and construction documents in collaboration with current
architectural firm including related narrative text, maps and visuals.
2. Furnish all
labor, materials and equipment to perform the work as described and services
in connection with the project in accordance with the requirements, criteria
and instructions contained in this document.
3. Provide
contractual arrangements, project submittal and design in accordance with
recognized criteria, regulations, manuals and other applicable standards;
and otherwise successfully provide all of the services required under this
Request for Proposals.
4. Commence work
promptly after issuance of a contract agreement with The Department in order
to complete project within approximately six (6) months.
5. Coordinate
input from relevant County agencies, which may include, but is not limited
to, the Porter County Planning Commission, Porter County Drainage Board and
the Porter County Highway Department.
Additionally, the
Contractor will be expected to meet regularly with the Porter County Parks
Foundation and the Porter County Park and Recreation Board to provide
progress reports and receive input and feedback. These meetings will be
scheduled to coincide with dates of already scheduled public meetings.
Submittal of Work
Final submittal
documents for the project shall include:
Ten (10) copies
of bids
All planning
provided in a .pdf format for the Department’s use
Projected
timetable (subject to change)
Request for
Proposals Issued: September 13, 2010
Pre-proposal
Conference (Call or in person) September 15, 2010, 3:00 pm CDT
Proposals Due:
September 24, 2010, 4:00 pm CDT
Interviews of
selected teams: * September 29, 2010
Final Contractor
selection: October 1, 2010
Contract
Execution: October 8, 2010
Contractor Begins
Work: October 11, 2010
Project
Completion: August 26, 2011
*number of
interviewed firms TBD by committee
Submission
Requirements:
Submissions
should include the following items:
Cover Letter
Provide a cover
letter indicating your firm’s understanding of the requirements of this
specific job proposal. The letter should be a brief formal letter from the
Proposer that provides information regarding the firm’s interest in and
ability to perform the requirements of this RFP.
Acceptance of
Conditions
Indicate any
exceptions to the terms and conditions, including the Scope of Services.
Project Plan
Include a
schedule of completion for the project, including major tasks and sub-tasks
to be accomplished. The schedule should show how long each phase will take.
Tab IV- Cost of
Services
Provide the total
not-to-exceed fee (including all direct and indirect costs) and estimated
work-hours for which your firm will provide the services described in this
RFP. Cost and work-hours should be broken down for each phase of services
according to the submitted business plan.
Compensation will
be based on hourly costs, using the firm’s schedule of hourly rates included
in a final Agreement with The Department.
Profit and
overhead should be incorporated into the hourly rates, which also include,
without limitation, all supplies, equipment, printing, copying, telephone,
computer, plotting, travel, mileage, drafting and other charges. No separate
or additional costs of any kind will be allowed. (Sub-Contractor fees may be
included as a separate item, without any mark-up.)
Submissions must
be received by 4:00 pm CDT on September 24, 2010 at:
Porter County
Administration Building
Parks and
Recreation Department
155 Indiana
Avenue, Suite 304
Valparaiso, IN
46383
Attn: Walter
Lenckos
All questions and
inquiries should be directed by email only to:
wlenckos@porterco.org
Selection
Criteria:
The selected
construction firm will exhibit extensive experience specific to the
construction of large, multi-objective buildings and related site planning;
professional background in the treatment of historic landscapes; the design
of outdoor park amenities, recreational ponds, pedestrian and bicycle
pathways, and urban design.
Bid Costs: The
Department will not be liable for any costs associated with responses to the
RFP.
(September 14, 21,
2010)